Notification to manufacture concrete panels

This publication is for: 
Employee / workerEmployer

An intention of notifcation to manufacture concrete panels must be advised to the WorkSafe Commissioner at least 10 working days before the first panel is to be cast; this includes panels manufactured on the construction site or at a precast yard or factory. The notification must:

  • specify where panels are to be manufactured;
  • the construction site at which panels will be used/installed.
WorkSafe
Form – notification
Last updated 01 Nov 2024

Last modified: